ERP Implementation/Development Consulting Services

Pacific Business Consulting has provided ERP implementation and development consulting services with a focus on Microsoft Dynamics NAV since 2001. We have a team of multi-national consultants and Japanese bilinguals with Microsoft certifications, and can support projects not only in Japan but also overseas.

 

Types of ERP Projects

Pacific Business Consulting ERP implementation projects can be classified into three types.

Implementation for Japanese companies in Japan
First is implementation for Japanese companies in Japan. We help develop systems to meet the requirements for sophisticated and complex business processes, enabling customers to boost competitiveness and productivity in the Japanese business environment.
Implementation for the overseas subsidiaries of Japanese enterprises
Second is implementation for the overseas subsidiaries of Japanese enterprises. We help our customers define and develop a corporate template in Japan. For implementation, we collaborate with trusted partners to ensure that local business requirements are fulfilled and system maintenance will be provided.
Implementation for foreign subsidiaries in Japan
Third is implementation for foreign subsidiaries in Japan. We can communicate effectively in English with corporate headquarters abroad and local senior executives in Japan, allowing our customers to complete implementation in a relatively short time.

 

 

Our Methodology

We maintain high quality in each project and deliver at full speed without leaving out tasks and perception gaps between the consultants.

Implementation Steps

sample

Component

Projects consist of the following 4 hierarchies.
We define ‘Phase’ as the highest hierarchy and ‘Step’, ‘Task’ and ‘Activity’ follow.

sample

Phase

Phase is the highest hierarchy in order to configure the project and there are 8 Phases below. Phase 1, 2, 3, 4, 5, 6 and 8 are carried out in sequence whereas Phase 7 – System Architecture is processed at anytime, depending on the projects.

sample sample

Step

Step is the next hierarchical element below Phase for configuring each phase and classified into 10 Steps.

Task

Task is the next hierarchical element below Step for configuring each step and correspond to ‘Work Package’ in a general WBS.

No Step No Task Deliverables
1 Project Initiation 1-1 Project Initiation Project Plan/WBS
/Project Plan
1-2 Creating WBS Project Schedule
2 Concept Explanation 2-1 Preparing Documents Manuals for Concept Training










Activity

Activity is the lowest hierarchical elements below Task for configuring each task and consists of who/when/where/what/how to/how long.

No Step No Task Activity Resource Man-day Due date
1 Project Initiation 1-1 Project Initiation Creating Project Plan Consultant-A 2.0 1/10
Reveiw Consultant-A & B 0.5 1/15
1-2 Creating WBS Creating WBS Consultant B & C 2.0 1/18
Reveiw Consultant B & D 1.0 1/25
2 Concept Explanation 2-1 Preparing Documents Preparing for training materials Consultant C 2.0 1/25
Environment for training Consultant C 2.0 1/28
Reveiw Consultant C & D 1.0 1/30